Have you noticed the new sand mounds at the end of each beach access? They're low, roughly triangular and planted with sea oats. They sit where the path opens toward the water, so it's easy to take them for landscaping. They're the main working part of the Dune Restoration Project the Town of Surfside started on May 11, 2026.
Every dune system has openings, because people have to get to the beach. Surfside's restoration put much of its effort into those openings. The low mounds are called diverter dunes, and they sit at the crossings you walk through to reach the sand. Most of the summer's work went into the dune itself and the path behind it.
Every crossing got its own mound
According to the Town's November 2026 Surfside Gazette, the diverter dunes were installed "to mitigate storm surge at breaks in the dune system." The Gazette describes their form this way:
"These features consist of independent, low, triangular-shaped sand mounds planted with sea oats."
The design does two jobs. The Gazette says the mounds are meant to reduce the energy of storm surge while still letting seawater recede. That limits how far water and sand travel inland during a major storm.
Surfside already had diverter dunes before this year, and the Town describes them as the first such features installed in Florida. The 2026 mounds add to that earlier set. The Town Manager's report of September 3, 2026, says the new ones were placed "at each beach access point," so the walk to the water now passes one at every crossing.
What the summer's work added, end to end
The dunes themselves were restored and raised. Native vegetation was replanted to hold the sand. The walking path behind the dune was improved along the whole stretch between 87th and 96th Streets.
The September 3 Town Manager report lists the pieces as follows:
| Element | Where it runs | Status on September 3 |
|---|---|---|
| Dune walking path | 96th Street south to 87th Terrace | Completed |
| Post-and-rope fencing | Along the path, starting at 96th Street and working south | Being installed behind the finished path sections |
| Diverter dunes | Each beach access point | Installed |
| Landscaping | East and west sides of the path | Next in the sequence, per the plans |
| Beach access mats | At the accesses | Next in the sequence |
| Signage | Along the beachfront | To be reinstalled after construction |
In its November Gazette, the Town reported the project as substantially completed. If your morning route was rerouted or roped off over the summer, the path between 87th Terrace and 96th Street is the part to walk again.
Who designed it, built it and paid for it
The September report says the Town Commission asked staff to pursue dune beautification and resiliency together. Kimley-Horn designed the improvements, and Dickerson Construction built them. As of that September 3 report, the construction contract stood at $2,549,630.60.
State money covered part of it. In February 2024, the Town Commission approved a grant agreement with the Florida Department of Environmental Protection. The grant came through FDEP's Beach Management Funding Assistance Program: $470,800, with Surfside required to match it with another $470,800 of its own. The Commission's resolution approving the agreement is public. The state grant comes to a little under a fifth of the construction contract. The grant and the Town's match together come to about 37 percent.
Those numbers show how the project was paid for. About two years and three months passed between the grant approval and the first day of construction.
Walking it this weekend, south to north
The path covers about a mile of beachfront, the length the Town gives for Surfside's beach. A parallel oceanfront bike path also runs from 87th Terrace to 96th Street. One way to walk it, from the south end:
- 87th Terrace. This is the south end of the rebuilt path. Count the diverter dunes as you pass each access on the way north. Each one is a short detour toward the water and back.
- 89th Street to 95th Street. This is the Beach Hard Path Fitness Trail, with eight outdoor workout stations along the hard path.
- A coffee stop near 95th Street. The Town's food and beverage directory lists Café Vert just south of 95th Street. It also lists Cine Citta Caffe, which the Town says has served Surfside for more than a decade. Bibi's Burgers is at 9505 Harding Avenue. The directory says Bagel Boss Surfside opened in summer 2025.
- 96th Street. The path ends here at the north end, which is also where the post-and-rope fencing started. On weekends, the Surfside Farmers Market sets up on the Surfside side of the 96th Street beach entrance. It runs Saturdays and Sundays from 9:30 a.m. to 3:30 p.m. through May, with fresh produce, specialty foods and artisan goods. The Town's Resort Tax Board sponsors it.
If you walk north and reach 96th Street mid-morning on a Saturday or Sunday, the market will be open.
For a quieter stop on the way home, the Town's parks information page lists Flamingo Garden at 92nd Street and Bay Drive, a small green space in the residential district.
On the Town calendar between now and mid-December
These dates come from the November Gazette and the Town's Parks and Recreation events listing:
- Saturday, November 21: Walk to End Alzheimer's
- First weekend of December: "Under The Stars" movie night with a screening of The Grinch, at 7 p.m. according to the Town's event page
- Sunday, December 13: Winter Wonderland
- Every Saturday and Sunday: Surfside Farmers Market at the 96th Street beach entrance, 9:30 a.m. to 3:30 p.m.
For more places to walk along the water in Greater Miami, see our guide to Miami's best-kept waterfront parks for picnics and views.
We follow projects like this one closely because they deal with the same question we face on every oceanfront lot: where the land meets the water, and how that edge is shaped and planted. At Jomed Construction, we've spent decades designing and building waterfront homes along South Florida's coast, from the first site study through the final landscape. If you're planning a home where the dune, the garden and the house have to work together, Request a Project Consultation and we'll start with your site.